Proses Manufaktur Segment Tunnel MRT Jakarta

WIKA KOBE
Sep 01, 2016


Tunnel lining is the wall of the tunnel. It usually consists of the precast concrete segment from rings. The precast concrete segment is a construction product produced by casting concrete in a reusable mold or form which is then cured in a controlled environment, transported to the site, and installed into place.
By Producing precast concrete segments in a controlled environment (typically referred to as a precast plant), the precast concrete segment is afforded the opportunity to properly cure and be closely monitored by plant employees. Utilizing a precast concrete segment offers many potential advantages over site casting of concrete. 

Production of segments Tunnel

 
figure 1. Manufacturing Plant
The trial assemble ring is built one above another to form three rings of tunnel lining and is bolted together on a flat level base. The rings are built one above the other and the radial joints are staggered by two-third of a segment. No packing or gaskets is used in the joints between segments. After assembly, the ring is checked according to check to make sure it conforms to design standards.

 
 figure 2.Trial Shop Assembly

Segment tunnels which is produced for Jakarta Mass Rapid Transit Undeground Section have 6.05 m Internal Diameter (ID) and 1.50 m Length with 25-30 cm thickness.

Mold
Outer Dia. ring
(m)
Length
(m)
Thickness
(cm)
Vol per ring
(m3)
Wt per ring
(tonnes)
Average weight/ segment
(kg)
No  of Segment
Per ring
Total Order
(ring)
CP 104-105
6.55
1.50
0.25
7.50
18.75
3125
6
3540
CP 106
6.65
1.50
0.30
9.00
22.50
3750
6
18 60
  
Manufacturing Process of Segmental Tunnel

The manufacturing process for the precast tunnel lining segment shall include the following steps :




 


 figure 3.Production Sequence Flowchart

a. Reinforcing Bar Installation

Fabricated rebar and accessories will be placed in the mold and checked for the position, arrangement and bindings.

Figure 4.  Install Rebar

b. Casting

Prior to casting, all adjustments, or minor rectification is carried out on the molds. Once all dimensions of the mold conform to design requirements, fresh concrete is poured into the molds.

Figure 5. Casting Concrete

In the concrete casting process, according to the operational standard, the vibrator is used 5-6 minutes per segment. During vibration, the concrete is checked if it is completely filling the mold and is not being over vibrated causing segregation. These molds require a lot of manpower to aid with the vibration and the compaction of concrete in the molds.

The minimum allowable concrete strength was 48 Mpa. After inspection and removal of any imperfections, the segments were moved to a stockyard that could accommodate whole rings, sufficient for about two months. Segments were stocked for a minimum of 28 days.
Compressive strength measures with the cube test in every 3 rings after 12 hours and the cylinder test at day 28 and must meet 48 MPa
The composition of cement and water mixture depends on the quality design of concrete that will be fulfilled.
The concrete must fulfill one of the requirements as follow :
•             SNI 15-2049-1994
•             ASTM C595
•             ASTM C845        

The Agregat must fulfill one of the requirements as follow:
•             ASTM C33
•             SNI 03-2461-1991

High performance concrete needs more control in hydration heat management, The higher mass of the concrete, the higher temperature there in the concrete. The difference in temperature inside the concrete and on the surface can make a tension strain and crack.

c.  Pre-Curing

The exposed concrete surface is covered with a set bag or canvas sheet to prevent drying effects. Below is a picture of the Pre-Curing process.

The exposed concrete surface is covered with a set bag or canvas sheet to prevent drying effects. Below is a picture of the Pre-Curing process. Every segment produced is then inspected for damages or defects at the time of demolding and along the repair line. The inspection is to determine and record whether the segment is acceptable and complies with the design requirements.
Figure 6. Pre-Curing

d. Strip Formwork

The required demolding strength of the segment should be attained in a period of approximately eight hours. Once the segment has attained sufficient demolding strength, the product will be removed from the mold by using a vacuum lifting device. Confirmation of sufficient demolding strength is achieved by testing the cubes that were cast before the concrete was poured into the mold for compressive strength.

The segment moving to the concrete bed can be done 12 hours from the demolding process and then stock moving to the water curing can be done 7 days.

Figure 7. Concrete Bad

e.  Water Curing
              
After demolding, cleaning, reinforcement installation, and concreting, the molds are automatically conveyed into a water curing tunnel. Both production methods achieve high production capacities if they are correctly adapted to the specific project requirements.
Figure 8. Water Curing

Water Curing to ensure cement hydration (reaction with water) including additives or substitutes that can occur optimally and expected the concrete quality can be achieved, and preventing the loss of moisture from the concrete, which can cause cracking.
Process be done in place the segment to the water curing can be done 7 days to obtain the required compressive strength of concrete (FC ').

f.  Temporary Storage

Every segment produced is then inspected for damages or defects at the time of demolding and along the repair line. The inspection is to determine and record whether the segment is acceptable and complies with the design requirements.

Figure 9 Segment Storage

To prevent steel forms rusting during a long period of storage coat them with a thin film of oil. Use a type that will not damage the concrete. (If you use sump oil, you will need to clean the steel forms before you reuse them).

Clean up any concrete spills and other debris from the pour site and surrounds. Also, make sure that the concrete surface is left in a safe condition. 


Komentar